144 | 1 | Bid Item 8A: Contaminated Soil to Landfill | 05/12/2025 09:09 AM | Road and Highway Builders, LLC | Response Published |
|
Question: To accurately price Bid Item 8A, bidders need clarification on the contamination level of the soil (e.g., parts per million of contaminants). Cost varies significantly with contamination level. Please provide expected contamination data or NDOT’s assumed level. Alternatively, would NDOT consider handling this as a force account item? |
Answer: The single dual-product tank will be constructed by Modern Welding in Fresno, California. Modern Welding will be responsible for loading the tank onto a transporter and delivering the tank to the Incline Maintenance Station. It is the contractor's responsibility to coordinate the delivery schedule, offload the tank from the transporter, and set the tank. |
|
145 | 2 | Bid Item 8B: Contaminated Soil Thermal Processing | 05/12/2025 09:11 AM | Road and Highway Builders, LLC | Response Published |
|
Question: Please advise on how to proceed with Bid Item 8B. Nevada Thermal Services is no longer in business, and bidders are unaware of any realistic alternatives for the thermal treatment of contaminated soil within Nevada. In light of this, should bid item 8B be removed? |
Answer: A heavy, broom finish is an acceptable alternative to the “light salt finish” for the P.C.C. stairs detailed on detail 1 of sheet D4.0. |
|
146 | 3 | Prime Coat on Aggregate Base | 05/12/2025 09:22 AM | Road and Highway Builders, LLC | Response Published |
|
Question: Does NDOT intend to add a separate bid item for prime coat on the aggregate base? If so, can NDOT also provide a list of approved prime coat materials for use within the Tahoe Basin area? |
Answer: • What size wire is this? #2 AWG size. • Where is the source? The source Panel “LA” is under the existing building #8 generator canopy structure (SE of Building #3). The 60-amp 2-pole Breaker #10/12 is labeled “Office/Brine Shed”. This breaker feeds the existing office building #2 and existing brine shed building #4. • What size pipe is this? 2” PVC SCH40. |
|
147 | 4 | NNPH Permit | 05/14/2025 09:41 AM | L.A. Perks Petroleum Specialists, I | Response Published |
|
Question: Have UST closure permits been obtained by NDOT from NNPH for this project. If not, are fees associated with UST closure permit the responsibility of the contractor or NDOT? |
Answer: Refer to Addendum #3 to the advertised bid documents for Department responses to inquiries #1 |
|
148 | 5 | NNPH AQMD Permit | 05/14/2025 09:54 AM | L.A. Perks Petroleum Specialists, Inc. | Response Published |
|
Question: Have AQMD "Minor Source Application for Permit to Construct" permits been obtained by NDOT from NNPH for this project. If not, are fees associated with the authority to construct permit the responsibility of the contractor or NDOT? Additionally, please confirm the awarded contractor is responsible for completing static pressure decay testing for the unleaded AST installation, as required by NNPH AQMD? |
Answer: |
|
149 | 6 | UST Residual Liquids | 05/14/2025 10:13 AM | L.A. Perks Petroleum Specialists, Inc. | Response Published |
|
Question: How much remaining fuel will be in the (2) UST's for disposal? |
Answer: Refer to Addendum #3 to the advertised bid documents for Department responses to inquiries #1 and #2 |
|
150 | 7 | RFI-Logistics and Handling of Fuel Assemblies and Tanks | 05/19/2025 10:00 AM | Road and Highway Builders, LLC | Response Published |
|
Question: The documentation indicates that NDOT will supply the fuel assemblies and tanks. To better understand the logistics and site readiness requirements, we would appreciate clarification on the following: Where are the tanks located? AND Is it the contractor’s responsibility to load the tanks? |
Answer: Refer to Addendum #3 to the advertised bid documents for Department responses to inquiries #1 and #2 |
|
151 | 8 | Concrete Requirements | 05/20/2025 02:15 PM | L.A. Perks Petroleum Specialists, Inc. | Response Published |
|
Question: Please clarify concrete requirements note "light salt finish" within detail 1 sheet D4.0. for the P.C.C. stairs. Is a heavy broom finish acceptable? |
Answer: |
|
152 | 9 | Electrical | 05/21/2025 08:32 AM | McCuen Construction, Inc. | Response Published |
|
Question: On I-E1.1 note 6 it shows to intercept existing electrical pipe for reroute. On I-E2.1 note 1 & 2 state to reroute and splice old wire in new N-9 box to new wire pulled back to source. • What size wire is this? • Where is the source? • What size pipe is this? |
Answer: |
|