User Login
Vendor
Registration
Vendor
Opportunities
Contractors/
Construction
Contractor Bulletins
Contractor Bulletin Subscription
Active and Awarded Contracts
Active Contracts Questions & Answers
Prequalified Contractors
Right To Lien
Return to previous page
Contract Details
Contract Documents
Contract Q&A
Award Info
Contract Details - 804-24
Contract # :
804-24
Project Number :
SPMS-000M-(362)
Project Scope :
Construction of new sander rack structures
District :
District 2
Funding Type :
State
Contract Time :
Working Days
Anticipated Working Days :
75
Status :
Executed
Project EA :
61167
Advertisement Date :
04/17/2024
Bid Opening Date and Time :
05/23/2024 02:30 PM
Engineer’s Estimate Range ($) :
R17 ($1,050,000.01 to $1,300,000.00)
Liquidated Damages :
250.00
SBE Goal % :
5
Location Details
Location Description :
Fairview and Gardnerville Maintenance Stations
County Name
Route Name
Begin MP
End MP
Carson City
CC
CC
Douglas County
DO
DO
NDOT Contact Details
Contract Services Manager :
Vanessa Pickles
Contract Documents - 804-24
Bid Items
No documents posted
Plans-Specifications-Invitation to Bid
No documents posted
Addenda
No documents posted
Prevailing wages and Qualified Products List (QPL)
No documents posted
Post Bid Opening Documents
No documents posted
Additional Informational Documents
No documents posted
Contract Q&A - 804-24
Export to PDF
Contract Q & A
QuestionID
Question #
Topic
Submit Date
Company Name
Status
155
1
FENCE
05/16/2024 02:42 PM
Reyman Brothers Construction
Response Published
Question: # 1: How tall does the fence need to be? The detail shows “Height as Specified”. #2: How wide does the gate need to be? The plans do not specify and the detail doesn’t address a specific width. #3: Does the fence require (3) strands of barbed wire on top? The corner and line post details show barbed arm adapters for the posts, but the fence detail does not show it having barbed wire attached and the written detail notes say “all post tops shall be fitted with suitable finials”. #4: The only mention of gauge of chain link fabric required is in the detail notes and requires 9ga 1” mesh when the fence is used as “no cut no climb fence”. Assumption would be that this is 2” mesh 9ga fabric unless otherwise specified…is that correct? #5: Are there any domestic material or America Iron & Steel (AIS) requirements?
Answer: A new version has been uploaded
156
2
Start Date
05/16/2024 02:44 PM
Reyman Brothers Construction
Response Published
Question: What is the Anticipated Start date for each of the Sander Rack Projects?
Answer: Standard detail TG-1 specifies the pole type and the sheet it is located on; further information can be found with the pole schedules . Furthermore, the pole in the design is there based on the requirements and any future needs.
157
3
GEOTECHNICAL REPORT / UNSUITABLE SOILS
05/23/2024 09:50 AM
MKD Construction Inc.
Unanswered
Question: ON NOTE 9, OF PLAN PAGES REFERENCED ABOVE, ALONG WITH STRUCTURAL CALCULATIONS FOR BOTH SITES, REQUIREMENTS OF PROCEEDURES TO MAKE NATIVE SOIL BEARING CAPACITY MEET SPECIFIED ALLOWABLE SOIL BEARING CAPACITY (FAIRVIEW 2.5 KSF; GARDNERVILLE 3.330 KSF) A FORMAL GEOTECHNICAL REPORT FOR EACH SITE, PRIMARYLY AT "5FT FOOTING ZONE OF INFLUENCE" AREA, PLEASE BE GENERATED AND PROVIDED. PLEASE PROVIDE GEOTECHNICAL REPORT FOR AREAS WHERE SANDER RACK FOOTINGS HAVE ALLOWABLE SOIL BEARING MINIMUM CALLED OUT. DELAY BID, TO GET INFORMATION TO BIDDERS.
Answer:
Award Info - 804-24
Awarded To :
Simerson Construction LLC
Award Amount ($) :
1,783,780.00
Enterprise Established Goal % :
5.00
Enterprise Established Goal Amount ($) :
89,189.00
Enterprise Committed Goal % :
5.50
Enterprise Committed Goal Amount ($) :
98,107.90
Award Date :
07/22/2024
Executed Date :
07/31/2024
Notice To Proceed Date :
08/26/2024
Performance Bond
Company Name
Address
Bond Number
GREAT AMERICAN INSURANCE COMPANY
301 E Fourth Street, Cincinnati, OH 45202
CA5771891
Payment Bond
Company Name
Address
Bond Number
GREAT AMERICAN INSURANCE COMPANY
301 E Fourth Street, Cincinnati, OH 45202
CA5771891