66 | 1 | CAD Files | 09/10/2025 01:02 PM | Granite Construction Company | Response Review In-progress |
|
Question: Are CAD files available for takeoff purposes? |
Answer: |
|
291 | 2 | GeoTech Report | 09/30/2025 09:49 AM | Granite Construction Company | Response Review In-progress |
|
Question: Is a Geotechnical Report available for takeoff purposes?
(question originally submitted to e-Bidding on 9/23/2025) |
Answer: |
|
293 | 3 | TRPA Permit | 09/30/2025 10:07 AM | Granite Construction Company | Response Review In-progress |
|
Question: Is the approved TRPA Permit for this project available for review? (question originally submitted to e-Bidding on 9/23/2025))
|
Answer: |
|
294 | 4 | Weekend Restrictions | 09/30/2025 10:14 AM | Granite Construction Company | Response Published |
|
Question: Can NDOT define onsite and offsite hauling? What work activities, work areas, and equipment will be prohibited 8:00 AM Friday morning(s) through 9:00 PM Sunday night(s)? (question originally submitted to e-Bidding on 9/23/2025) |
Answer: All lanes shall remain open and unimpeded to public traffic on SR 28 from 8:00 A.M Friday morning(s) through 9:00 P.M. Sunday night(s). Hauling would include any onsite deliveries and offsite material disposals resulting in any impact to public traffic on SR28. |
|
295 | 5 | Work Outside TRPA Grading Season | 09/30/2025 10:22 AM | Granite Construction Company | Response Review In-progress |
|
Question: What work activities are allowed outside of the TRPA Grading Season (Oct 15, 2026 - May 1, 2027)? Clarification on what work is acceptable on the charged working days in November, March, and April would be helpful. (question originally submitted to e-Bidding on 9/23/2025) |
Answer: |
|
296 | 6 | Migratory Bird Nesting Season | 09/30/2025 10:30 AM | Q&D Construction LLC | Response Review In-progress |
|
Question: With the NTP of 5/4/26 in the middle of the nesting season (January 1st thru September 30th) outlined in section 108.03 of the special provisions, and the near 100% probability that nests will be found in any number of the 548 trees designated for removal, will the NTP be moved to better reflect the nesting season as outlined in Migratory Bird Treaty Act, Bald Eagle Act and NRS? In lieu of moving the NTP, will the department apply for and procure the US Fish and Wildlife Incidental Take Permit to allow construction to start within the 2026 Season? (question originally submitted to e-Bidding on 9/25/2025) |
Answer: |
|
297 | 7 | Electrical & signal quantities | 09/30/2025 10:36 AM | Summit Line Construction, Inc. | Response Review In-progress |
|
Question: Upon reviewing the contract documents, the planned electrical quantities do not match the electrical bid item quantities. Please confirm the bid item quantities are accurate. (question originally submitted to e-Bidding on 9/26/2025) |
Answer: |
|