| 769 | 1 | Plants (Group A-5) | 08/26/2026 08:22 AM | Soil-Tech, Inc. | Response Published |
|
| Question: Please confirm the official plant quantity and group designation. The planting plan indicates 125 plants under Group A-1, while the Estimate of Quantities indicates 140 plants under Group A-5. |
| Answer: The estimate will be updated to reflect the plan quantity of 125 Group A-1. Group A-5 will be removed. This discrepancy will be addressed in an upcoming submittal. |
|
| 770 | 2 | Quantites listed on sheet 3D | 08/28/2026 02:45 PM | Q&D Construction LLC | Response Published |
|
| Question: When reviewing the plan quantities on plan sheet 3D and the bid item quantities. It appears that none of these match. can you please confirm what quantities are supposed to be used? Also, on this sheet it lists Composite Surface removal which should be its own bid item if that is the intention for the quantity listed. |
| Answer: The quantities to be used are the quantities on sheet 3D. Composite Surface Removal has been removed, and those quantities are added to Roadway Excavation. The estimate will be updated in an upcoming addendum. |
|
| 771 | 3 | Asphalt Type | 09/01/2026 06:56 AM | Q&D Construction LLC | Response Published |
|
| Question: The Plans list a Type 2C asphalt but the bid item is a Type 2. Please confirm. |
| Answer: The item is Type 2 and will be corrected in an upcoming addendum. |
|
| 772 | 4 | 623 2870 Cellular Telephone modem | 09/01/2026 10:53 AM | Sierra Transportation Technologies | Response Published |
|
| Question: Please clarify which Cell modem option is required for this project. |
| Answer: Cell Modem Option 1 is required for all cell modems on this project. |
|
| 773 | 5 | 623 0185 Traffic Management System | 09/01/2026 10:53 AM | Sierra Transportation Technologies | Response Published |
|
| Question: Please provide requirements for what is needed for the traffic Management System. |
| Answer: This item will be deleted in an upcoming addendum. |
|
| 774 | 6 | 623 1130 Antenna | 09/01/2026 10:53 AM | Sierra Transportation Technologies | Response Published |
|
| Question: Please provide requirements for what is needed for the Antenna bid item |
| Answer: This item will be deleted in an upcoming addendum. |
|
| 775 | 7 | DRAINAGE | 09/02/2026 08:53 AM | C AND S COMPANY | Response Published |
|
| Question: ON SHEET 19 NOTE D2 CALLS FOR RCP AND PRECAST END SECTIONS, ON SHEET DS3 THE CALL OUT IS SAFETY END SECTIONS, CAN YOU PLEASE CLAIRIFY IF THIS IS SUPPOSED TO BE PRECAST OR CMP?
6042445 D2 STA: "LE" 315+23 |
| Answer: The correct bid item is 603 1050 (24-INCH PRECAST END SECTION). This will be addressed in an upcoming addendum. |
|
| 776 | 8 | ITS Pole Quantities | 09/04/2026 11:12 AM | Summit Line Construction, Inc. | Response Published |
|
| Question: Plan sheet ITS 06A shows an 80' ITS pole and a 30' ITS pole, however, the structures list shows just an 80' ITS pole, can you please clarify the quantities for both of the 80' and 30' ITS poles? |
| Answer: Sheet ITS06A calls for one (1) 80-foot ITS pole only. The plan notes is unclear and may be interpreted as also requiring a 30-foot ITS pole. The plan note will be revised for clarity in an upcoming addendum |
|
| 777 | 9 | Ornamental Lighting Detail | 09/04/2026 11:12 AM | Summit Line Construction, Inc. | Response Published |
|
| Question: Can you please provide the special detail for the ornamental lighting called out on sheet LT 03? |
| Answer: This will be provided in an upcoming addendum. |
|
| 778 | 10 | NV Energy Plans | 09/04/2026 11:12 AM | Summit Line Construction, Inc. | Response Published |
|
| Question: Can you please provide the NV Energy plans as stated on sheet ITS 33? |
| Answer: This will be provided as additional information after the contract is awarded. |
|
| 779 | 11 | Conduit Quantities | 09/04/2026 11:13 AM | Summit Line Construction, Inc. | Response Published |
|
| Question: Can you please confirm your conduit quantities, my take-offs are resulting in substantial differences (roughly 30%). |
| Answer: Please bid per structure list. |
|
| 780 | 12 | Traffic Management System Clarification | 09/04/2026 01:59 PM | Summit Line Construction, Inc. | Response Published |
|
| Question: Could you please clarify what Bid Item 623 0185 – Traffic Management System entails? |
| Answer: This bid item has been deleted and will be addressed in an upcoming addendum. |
|
| 783 | 13 | RWIS | 09/09/2026 02:24 PM | Vaisala Inc. | Response Published |
|
| Question: How many RWIS stations are being bid. The estimated quantities document states one but the Plans state two. |
| Answer: Two RWIS stations are included in the project. The bid item is lump sum; therefore, the quantity shown as 1 in the Structure List represents the complete work for both stations. Please bid based on two RWIS stations. |
|
| 784 | 14 | RWIS | 09/09/2026 02:24 PM | Vaisala Inc. | Response Published |
|
| Question: Special Provisions 623.02.34 Road and Weather Information System, under B, request non-invasive surface detections sensors, but they are not listed in the plans identified on RWIS Site Detail Plans sheet ITS26 shows non-invasive sensor and one in-pavement Road Sensor. Please confirm which sensors are required. Additionally, there is a Barometric Pressure listed in the Special Provisions but dot not show in the plans, please advise if these should be included. Finally, the plans do not show a visibility sensor but is listed in the special provisions. |
| Answer: Non-invasive surface detection sensors are not required for this project. Sheet ITS26 is intended primarily to provide mounting and installation information, including mounting heights. For the specific devices required at each site, please refer to the RWIS Schedule. The revised RWIS Schedule will be provided in an upcoming addendum. |
|
| 785 | 15 | RWIS | 09/09/2026 02:24 PM | Vaisala Inc. | Response Published |
|
| Question: Please confirm if RWIS will be Solar Powered or AC powered. If two RWIS are required, is it one of each. |
| Answer: Two RWIS stations are required. The RWIS station shown on ITS05 shall be solar powered, and the RWIS station shown on ITS06 shall be AC powered. |
|