?
Active Contracts Questions & Answers

Prospective bidders and other interested parties may have questions regarding contract documents, plans and specifications. The Contract Questions and Answers process allows for questions to be directed in writing to the Project Manager, and for all questions and answers to be posted publicly here. Enter information in the box below to search for a contract's existing Q & A, or select New Question to ask a question. Your question will be automatically sent to the Project Manager for the contract you select. Please submit your questions no later than 4:00pm PST 10 days prior to bid opening to ensure your question is answered. Questions received after this time will be answered at the discretion of the Project Manager. Contracts will be available in the New Question window until bid opening.


Contracts #
select


Keyword



Question #TopicSubmit DateCompany NameStatus
      
Contract #: 4564
 7691Plants (Group A-5)08/26/2026 08:22 AMSoil-Tech, Inc. Response Published
Question: Please confirm the official plant quantity and group designation. The planting plan indicates 125 plants under Group A-1, while the Estimate of Quantities indicates 140 plants under Group A-5.
Answer: The estimate will be updated to reflect the plan quantity of 125 Group A-1. Group A-5 will be removed. This discrepancy will be addressed in an upcoming submittal.
 7702Quantites listed on sheet 3D08/28/2026 02:45 PMQ&D Construction LLC Response Published
Question: When reviewing the plan quantities on plan sheet 3D and the bid item quantities. It appears that none of these match. can you please confirm what quantities are supposed to be used? Also, on this sheet it lists Composite Surface removal which should be its own bid item if that is the intention for the quantity listed.
Answer: The quantities to be used are the quantities on sheet 3D. Composite Surface Removal has been removed, and those quantities are added to Roadway Excavation. The estimate will be updated in an upcoming addendum.
 7713Asphalt Type09/01/2026 06:56 AMQ&D Construction LLC Response Review In-progress
Question: The Plans list a Type 2C asphalt but the bid item is a Type 2. Please confirm.
Answer:
 7724623 2870 Cellular Telephone modem09/01/2026 10:53 AMSierra Transportation Technologies Response Review In-progress
Question: Please clarify which Cell modem option is required for this project.
Answer:
 7735623 0185 Traffic Management System09/01/2026 10:53 AMSierra Transportation Technologies Response Published
Question: Please provide requirements for what is needed for the traffic Management System.
Answer: This item will be deleted in an upcoming addendum.
 7746623 1130 Antenna 09/01/2026 10:53 AMSierra Transportation Technologies Response Review In-progress
Question: Please provide requirements for what is needed for the Antenna bid item
Answer:
 7757DRAINAGE09/02/2026 08:53 AMC AND S COMPANY Response Review In-progress
Question: ON SHEET 19 NOTE D2 CALLS FOR RCP AND PRECAST END SECTIONS, ON SHEET DS3 THE CALL OUT IS SAFETY END SECTIONS, CAN YOU PLEASE CLAIRIFY IF THIS IS SUPPOSED TO BE PRECAST OR CMP? 6042445 D2 STA: "LE" 315+23
Answer:
 7768ITS Pole Quantities09/04/2026 11:12 AMSummit Line Construction, Inc. Response Review In-progress
Question: Plan sheet ITS 06A shows an 80' ITS pole and a 30' ITS pole, however, the structures list shows just an 80' ITS pole, can you please clarify the quantities for both of the 80' and 30' ITS poles?
Answer:
 7779Ornamental Lighting Detail09/04/2026 11:12 AMSummit Line Construction, Inc. Response Review In-progress
Question: Can you please provide the special detail for the ornamental lighting called out on sheet LT 03?
Answer:
 77810NV Energy Plans09/04/2026 11:12 AMSummit Line Construction, Inc. Response Review In-progress
Question: Can you please provide the NV Energy plans as stated on sheet ITS 33?
Answer:
 77911Conduit Quantities09/04/2026 11:13 AMSummit Line Construction, Inc. Response Review In-progress
Question: Can you please confirm your conduit quantities, my take-offs are resulting in substantial differences (roughly 30%).
Answer:
 78012Traffic Management System Clarification09/04/2026 01:59 PMSummit Line Construction, Inc. Response Review In-progress
Question: Could you please clarify what Bid Item 623 0185 – Traffic Management System entails?
Answer:
1
Page size:
 12 items in 1 pages
  • NoFilter
  • Contains
  • DoesNotContain
  • StartsWith
  • EndsWith
  • EqualTo
  • NotEqualTo
  • GreaterThan
  • LessThan
  • GreaterThanOrEqualTo
  • LessThanOrEqualTo
  • Between
  • NotBetween
  • IsEmpty
  • NotIsEmpty
  • IsNull
  • NotIsNull
  • Custom