Active Contracts Questions & Answers

Prospective bidders and other interested parties may have questions regarding contract documents, plans and specifications. The Contract Questions and Answers process allows for questions to be directed in writing to the Project Manager, and for all questions and answers to be posted publicly here. Enter information in the box below to search for a contract's existing Q & A, or select New Question to ask a question. Your question will be automatically sent to the Project Manager for the contract you select. Please submit your questions no later than 4:00pm PST 10 days prior to bid opening to ensure your question is answered. Questions received after this time will be answered at the discretion of the Project Manager. Contracts will be available in the New Question window until bid opening.


Contracts #
select


Keyword



Question #TopicSubmit DateCompany NameStatus
      
Contract #: 4553
 6391CAD Files12/03/2025 04:05 PMGranite Construction Company Response Review In-progress
Question: Are CAD files available for takeoff purposes?
Answer:
Contract #: 4548
 5971CAD Files10/15/2025 12:35 PMGranite Construction Company Response Published
Question: Please provide CAD files for takeoff purposes.
Answer: The CAD files have been uploaded.
 6082Class AA Concrete Curb (Special)10/29/2025 06:33 AMQ&D Construction LLC Response Published
Question: Are there any available details for this Special curb?
Answer: Details for the Special Curb will be included in an addendum.
 6113Signal Trench Detail10/31/2025 10:28 AMSummit Line Construction, Inc. Response Published
Question: Current trench detail in the signal drawings is the TMWA water detail. Please clarify if that's the detail being used for the signal trenching.
Answer: Use of this detail is called out on the plan sheets and is to be used when trenching near TMWA facilities. For all other trenching, refer to sheet ITS49.
 6124Removal of Sound Wall11/14/2025 09:41 AMQ&D Construction Response Published
Question: Does the removal of sound wall bid item include the removal of the barrier rail under the sound wall? Is there any footing underneath the barrier rail and if so, is that included in this removal item also?
Answer: Removal of soundwall and all its structural components are inclusive to the bid item in accordance with section 202 in the Standard Specifications.
       5                     Question 5 is withdrawn
 6146Sign Sheets ST29 & TS31 Natina Stain OH Sign Structures11/18/2025 01:26 PMNevada Barricade & Sign Co,. Inc. Response Published
Question: Both plan sheets ST29 & TS31 include a note stating: “ALL NEW SIGN POSTS ON THIS SHEET SHALL RECEIVE NATINA GALVANIZED METAL COATING.” However, the only sign structure specifically calling out Desert Varnish is on plan sheet TS50. Please confirm whether Sign Structures 29-1, 29-2, and 31-5, as shown on these plan sheets, are also required to receive Natina stain as indicated in the note. If so, please update the overhead signing plan sheets to reflect Natina stain for the listed structure numbers.
Answer: Yes, please see the note on plans sheets TS29, TS30, TS30A and TS31. Also Per 212.02.12, Apply Natina to all sign posts, signal posts, and metalwork at the Lemmon Valley Interchange….XN 865+00 to 885+00 and XS 860+00 to 885+00. Sign structures are metal work and Natina shall be applied to sign structures in this area.
 6157Sign Sheets ST29 & TS31 Natina Stain Ground Mounted Signs11/18/2025 01:26 PMNevada Barricade & Sign Co,. Inc. Response Published
Question: Per the Note in the Special Provision for the Desert Varnish "NATINA STAIN" is appears that only the Ground Mounted Metal Support Signs on plan sheets ST30 & ST30A are to be stained. Does NDOT also want all the Ground mounted signs shown on TS29 & TS31 to be Stained as well per the required note?
Answer: Yes, please see the note on plans sheets TS29, TS30, TS30A and TS31. Also Per 212.02.12, Apply Natina to all sign posts, signal posts, and metalwork at the Lemmon Valley Interchange….XN 865+00 to 885+00 and XS 860+00 to 885+00. Sign structures are metal work and Natina shall be applied to sign structures in this area.
 6168Sound Wall Access Doors11/18/2025 03:52 PMGranite Construction Company Response Published
Question: What are the dimensions of the Sound Wall Access Doors? They are not shown on the detail on SW41.
Answer: Sound Wall Access Doors should be 4' x 6'
 61791. Riprap Aprons at Drainage Outlet11/18/2025 05:06 PMGranite Construction Company Response Published
Question: Plan Sheets, Profile Sheets, and Structures List quantities do not match for riprap outlet aprons. Can NDOT please advise which quantity is correct and update the plan sheets, profile sheets, and structures lists accordingly?
Answer: The quantities will be updated in an addendum to the following: Drainage Excavation: Increase by 46 CUYD Geotextile: Increase by 38 SQYD Class 300 Riprap: Decrease by 36 CUYD Class 400 Riprap: Increase by 73 CUYD Class 300 Riprap Bedding: Decrease by 12 CUYD Class 400 Riprap Bedding: Increase by 21 CUYD
 61810Pavement Reinforcing Fabric11/19/2025 12:11 PMGranite Construction Response Published
Question: The contract documents call out for pavement reinforcing fabric to be placed at a 3” depth centering the joint at the moment slabs for the sound walls. The note states that a fine milled surface will be required in all areas with pavement reinforcing fabric with additional tack coat. If the pavement reinforcing fabric straddles the joint and 3’ of the fabric will be on new dense grade surface, please clarify whether a fine milled surface will be required on the new dense grade surface prior to placement of the reinforcing fabric.
Answer: The fine milled surface will only be required when the fabric is being placed on a milled surface, it will not be required when being placed on new dense grade.
 61911Maintenance of Traffic11/19/2025 12:20 PMGranite Construction Response Published
Question: During the pre-bid meeting, a temporary traffic control configuration plan with associated temporary paving quantities was available. Can NDOT please provide that exhibit?
Answer: The MOT plans have been uploaded to be used for informational purposes. The plantmix quantity calculated for temporary paving is 8890 Tons.
 62012Special Provision Section 20811/20/2025 08:54 AMQ&D Construction Response Published
Question: Consider payment for rolling and proof rolling or for the correction of any subgrade weakness or deficiencies disclosed by the proof rolling operation subsidiary to the price bid for the "Excavation" item. Will the Fabric and Rock materials described above this paragraph be compensated at their respective bid item prices?
Answer: Yes, the Fabric and Rock materials described above this paragraph will be compensated at their respective bid item prices.
 62113GUARDRAIL- BARRIER RAIL CONNECTION (TRIPLE CORRUGATION)11/20/2025 04:12 PMNevada Barricade & Sign Co., Inc. Response Published
Question: Can NDOT please add bid item 6180400 GUARDRAIL- BARRIER RAIL CONNECTION (TRIPLE CORRUGATION) 9-each to the bid schedule? By adding this bid item this will allow for the proper installation / connection points from the barrier rail to the guardrail, and end anchor assemblies. You cant install the end anchors assembles shown on the plans directly to the Barrier Rail with out the Barrier Rail Connections.
Answer: There are no connections between barrier rail and guardrail on the project. Also refer to the response for RFI #14.
 62214Bid Item 6180270 TRAILING END ANCHOR11/20/2025 04:12 PMNevada Barricade & Sign Co., Inc. Response Published
Question: The bid item is for 9-each; however, 1 was left off on the end of the guardrail run on plan Construction plan sheet 17 there should be 10-each. Can NDOT please update the quantity to 10-each?
Answer: The quantity was incorrect and should only have been used at the one location identified as stated on plan sheet 17. The quantity will be adjusted from 9 to 1 in an addendum.
 62315Bridge 1770 Form Liner Pattern11/20/2025 04:58 PMGranite Construction Company Response Published
Question: Sheet LD108 pattern calls for Reckli 2/186 Dalarna form liner on the wingwalls. The structures list on sheet LD110 specifies Medium Bush Hammer 1615 pattern. Please verify which one is correct.
Answer: The callout on LD110 under heading i-770 Bridge-Lemmon, XN north wing wall CIP should read Reckli2/186 Dalama, not Medium Bush hammer 1615. Wingwalls should be a pattern matching Reckli 2/186 Dalarna pattern per LD108.
 62416Bridge Integral Color11/20/2025 04:58 PMGranite Construction Company Response Published
Question: Sheet LD108 calls out integral color for the bridge rail and wingwalls for the north side. Sheet LD109 calls out to paint the bridge rail. Please verify whether all new bridge rail gets integral color or paint. Also verify the wingwalls on bridge 1770 get integral color or paint.
Answer: Wingwalls shall be painted. For durability and aesthetic purposes, some integral rail will be painted although all new rail shall be integral. On Sheet LD1019, new rail shall be integral. Since existing rail is being painted in this area, the new rail will also be painted. The solid line around the rail on LD109 depicts paint color wooden peg.
 62517Pre-Bid Agenda Discrepancy versus Project Documents11/25/2025 09:14 AMNorth Valley Constructors, a Joint Venture Response Published
Question: During the Mandatory Pre-Bid meeting, information and direction were provided that directly conflicted with the Project Documents. Please advise which information supersedes the other
Answer: Contract documents supersede any information or direction presented at the Pre-Bid Meeting.
 62618Image Panels11/25/2025 12:13 PMGranite Construction Company Response Published
Question: Can you please confirm the thickness of the material required for the Image Panels on Sheets LD111 to LD114. Also, can you confirm all image panels and tubing on the project is to be A36 Mild Steel?
Answer: Per details T1 and T2 on S002, the bid item Image Panels are ¼” A36 steel with powder coat. The pipe spacer between panels is ½” A53 Grade B. Image panels are to be placed on bridge walls as shown on the plans. For the metal cutouts that are part of the bid item Decorative Structure, the size varies from 3/8” to ¼” depending on structural needs. Please refer to the General Structural Notes on S001 for each type of structural steel used. The tubing on the project (HSS4x4x1/4,HSS5x5x5/16, and HSS4x4x5/16) are to be ASTM A500, Grade C. Please also refer to the Special Provisions for any additional requirements as well as the individual pieces.
 62719Image Panels11/25/2025 12:36 PMGranite Construction Company Response Published
Question: A single tube base plate configuration is missing from Sheet S201, Please provide dimensions.
Answer: For each column, there are two baseplate configurations provided on sheet S201. For adjacent columns that are located 1’-1” (or less) apart, the alternative baseplate configuration with (2) columns is provided. The rest follow the baseplate configuration for the singular column as shown on the plans.
 62820Slope Paving and Riprap11/26/2025 11:01 AMAmes Construction Response Published
Question: Golden Valley Interchange & Stead Boulevard both have existing sloped concrete paving sections, see Roadway Plan sheets 6 & 17. On the removal drawings (sheets SP2, SP3 & SP14) the slope paving sections are not listed as being removed. However, on the Roadway Plans both underpasses are being shown as widened into the sloped concrete paving. Additionally, the Landscape Site Plan drawings (Sheets L306, & L336) show riprap being placed over all of the existing sloped concrete paving sections. Please confirm removal of all concrete sloped paving at Golden valley Interchange and Stead Boulevard.
Answer: The quantity for slope paving removal for the Golden Valley Interchange is in the Bridge Sheets (B100 and B101). The slope paving removal quantity for Stead Blvd will be included in an addendum.
 62921Riprap11/26/2025 11:01 AMAmes Construction Response Review In-progress
Question: On the landscape Site Plan drawings sheet numbers L318 & L319, new rip rap is called out to be placed around the existing bridges at Lemmon Drive. Current site conditions show that there is already riprap placed over a majority of the noted areas in the plans. Please confirm that existing riprap needs to be replaced.
Answer:
 63022CMO Form NDOT 020-09511/27/2025 08:35 AMSierra Transportation Technologies Response Review In-progress
Question: For products that are specifically called out on the plans or in the specifications and not manufactured in its entirety within the USA, is a CMO(Certificate of Origin) required? Can NDOT obtain a reusable CMO from the manufactures they are requesting products from? This information doesn't change and could be used on future projects. This would aide in assisting the contractors and suppliers from the difficult to almost impossible task of getting this form signed on each project. Many of the manufactures are refusing to sign the form. Also many have trouble calculating or will not calculate the dollar amount of foreign materials within the project. Contractors cant get payment until the CMO is received causing payment issues with contractors, subcontractors and suppliers.
Answer:
 63123Bridge Barrier & Overhang Removal11/30/2025 03:23 PMGranite Construction Company Response Review In-progress
Question: The special provisions allow for full closures on Golden and Lemmon for falsework and concrete placement. It does not specify whether full road closures will be allowed for removal of the bridge barrier and overhang. Completing removals without closing the road to traffic presents safety risks to the traveling public and should be considered. Will NDOT allow additional full closures for this work? If so, how many closures will be allowed?
Answer:
 63224Soundwall In Fill Concrete Requirements12/01/2025 09:30 AMNorth Valley Constructors, a Joint Venture Response Review In-progress
Question: Is it the intention of NDOT to require shrinkage testing of the infill concrete for the soundwalls?
Answer:
 63325CIPP Lining Callouts12/01/2025 06:03 PMInsituform Technologies, LLC Response Published
Question: Map page D12A shows that line 12 is to be rehabilitated using CIPP but map page D12 shows the arrow pointing to a MH or catch basin, can the client show which line is to be rehabilitated?
Answer: Note 12 on sheets D12A, DS29 & DS29A, defines the work to be performed and Sheet DS29A further defines the total length of culvert to be lined after other work in the construction note has been completed.
 63426Question Deadline Extension12/01/2025 06:04 PMInsituform Technologies, LLC Response Review In-progress
Question: The file "4548 Invitation to Bid" states that the bid question deadline is 10 days prior to the bid date. Can the question deadline be extended?
Answer:
 63527CIPP Rehabilitation Clarification Map Page D312/01/2025 07:14 PMInsituform Technologies, LLC Response Published
Question: Map page D3 calls out line 34 as a catch basin, but CIPP rehab required, can the line to be rehabilitated be clarified?
Answer: Note 34 on sheets D3A, DS7 & DS7A, defines the work to be performed and Sheet DS7 further defines the total length of culvert to be lined after other work in the construction note has been completed.
 63628CIPP Rehabilitation Clarification Map Page D912/01/2025 07:15 PMInsituform Technologies, LLC Response Published
Question: Map page D9 calls out 202 LF on 36" pipe on number 8 but the plans look very different can you confirm this length?
Answer: Note 8 on sheets D9A, DS22 & DS22A define the culvert length as 202’. This is consistent with what is shown on sheet D9.
 63729CIPP Rehabilitation - Depths of Pipes12/01/2025 07:15 PMInsituform Technologies, LLC Response Published
Question: Can you confirm all the depths of the pipes to rehabilitated using CIPP? It appears to be off in some locations.
Answer: Cover depths have been estimated with the best available information and has been included in the construction notes where applicable. Some of the culverts to be lined are also profiled in the DP-sheets which can be referenced for clarity. The lining subcontractor should confirm actual cover depths during culvert cleaning and pre-lining inspection/repair activities. Culvert lining design should be completed based on field measured cover depths.
 63830CIPP Rehabilitation - Verification of Scope12/01/2025 07:15 PMInsituform Technologies, LLC Response Published
Question: The chart and the map pages don't match up with diameter or length for CIPP segments, can you confirm which one is correct?
Answer: No inconsistencies are noted between the info listed in the plan view, construction notes and related bid items. The lining subcontractor should confirm culvert sizes during cleaning and pre-lining inspection/repair activities and note any discrepancies at that time with the engineer prior to ordering and preparing lining materials for installation.
 64031CORR./METAL PIPE12/04/2025 09:11 AMYMSC Inc. DBA Prime Supply 1 Response Review In-progress
Question: #1: What are the flared ends connecting to (CMP, Concrete..)? #2: WHAT TYPE OF PIPE IS BEING USED FOR THE DOWNDRAIN? #3: DO THE FLARED ENDS REQUIRE SAFETY SLOPES?
Answer:
1
Page size:
 32 items in 1 pages
  • NoFilter
  • Contains
  • DoesNotContain
  • StartsWith
  • EndsWith
  • EqualTo
  • NotEqualTo
  • GreaterThan
  • LessThan
  • GreaterThanOrEqualTo
  • LessThanOrEqualTo
  • Between
  • NotBetween
  • IsEmpty
  • NotIsEmpty
  • IsNull
  • NotIsNull
  • Custom